1. Shawn is the project manager of the WHT Project for his company. In this project Shawn's team reports that they have found a way to complete the project work for less cost than what was originally planned. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes to the project management plan accordingly. What type of risk response has been used in this instance?
A) Enhancing B) Accepting C) Avoidance D) Exploiting
2. Which of the following sub-processes of Capacity Management is concerned with the management of the individual components of the IT Infrastructure?
A) Capacity Management Reporting B) Business Capacity Management C) Service Capacity Management D) Resource Capacity Management
3. You work as the project manager for Bluewell Inc. You are working on NGQQ Project for your company. You have completed the risk analysis processes for the risk events.You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?
A) Risk transference B) Risk avoidance C) Risk acceptance D) Risk mitigation
4. Which of the following are the advantages of IT Resource Management? Each correct answer represents a complete solution. Choose all that apply.(Select 3answers)
A) It develops the IT service quality and effectiveness. B) It reduces the IT project complexity. C) It reduces the enterprise risks. D) It provides customer organization to construct the Request for Proposal (RFP).
5. Which of the following domains of COBIT covers the use of information & technology, and how best it can be used in a company to help achieve the company's goals and objectives?
A) Deliver and Support B) Acquire and Implement C) Plan and Organize D) Monitor and Evaluate